Industrial sockets and machine supplies for workshops and units

A new compressor, saw, lift or packing machine usually arrives with a data plate and a length of cable, and an assumption that there is somewhere suitable to connect it. Getting the supply right is part of installing the machine, not an afterthought.

Last updated

Short answer

Machinery is supplied either through an industrial plug and socket or by a fixed connection through a local isolator. The supply is designed from the machine's data plate: voltage, number of phases, full-load current and any starting current. The circuit, protective device, isolation and cable route are then selected to BS 7671. Part P does not apply to industrial premises, but the Electricity at Work Regulations 1989 and the work equipment regulations place duties on the employer, so the supply should be designed, installed and tested by a competent, qualified electrician.

Reading the data plate

Every machine carries a plate stating its supply voltage, whether it is single-phase or three-phase, its frequency, and its rated current or power. Some also state the size of protective device the manufacturer requires. Motors draw a much higher current for a moment as they start, and the manual may give a figure for that as well.

That information decides everything else. A photograph of the plate and the relevant page of the manual, sent before the site visit, lets the electrician check the supply and distribution board in advance and arrive with the right equipment.

Industrial plugs and sockets

Industrial connectors, often called commando sockets, are round, robust and colour-coded by voltage. Blue indicates a single-phase supply at normal mains voltage; red indicates a three-phase supply. Yellow connectors are used for reduced-voltage supplies to site tools. Within each colour, connectors are made in several current ratings, and the sizes are deliberately not interchangeable, so a plug of one rating will not fit a socket of another.

Three-phase connectors come with four or five pins. A five-pin connector carries three phases, neutral and earth; a four-pin connector has no neutral. The machine determines which is needed. Sockets can be supplied with a switch that is mechanically interlocked with the plug, so the plug cannot be inserted or withdrawn while the socket is live, which is good practice for larger ratings.

Fixed connections and isolators

Larger machines, and machines that stay in one place, are normally connected permanently. The cable runs to an isolator mounted beside the machine, and from there to the machine's terminal box. The isolator lets a maintenance engineer disconnect the supply and secure it in the off position with a padlock while working on the equipment.

The isolator is there for safe maintenance. It is separate from the machine's own controls and emergency stop, which are part of the machine and the manufacturer's responsibility. The electrician supplies and tests the installation up to the machine's terminals unless agreed otherwise.

Single-phase or three-phase

Most substantial machinery is three-phase, because three-phase motors are smaller, smoother and more efficient for a given output. If a unit has only a single-phase supply, the options are a machine built for single-phase, a supply upgrade from the network operator, or in some cases a converter or variable-speed drive supplied with the machine. Each has limitations, and the right answer depends on the machine. Our guide to three-phase electrics for warehouses covers the supply side.

Want a fixed written quote? Call 01235 430442 or send us the details.

Protection and motor circuits

The protective device has to let the motor start without tripping, yet still protect the cable. Devices are therefore chosen with a characteristic suited to motor loads, and the cable is sized accordingly. Many machines include their own overload protection and starter; where they do not, a starter is installed as part of the supply.

Socket-outlets up to a certain rating require RCD protection under BS 7671. Machines with variable-speed drives produce small leakage currents and can cause unwanted tripping of some RCDs, so the type of device is selected with the drive in mind. This is a design matter to be raised early if the machine includes a drive.

Cable routes and containment

  • Armoured cable on tray or cleated to the structure is usual for longer runs.
  • Final connections to machines that vibrate are made in flexible conduit or flexible cable.
  • Routes are kept clear of forklift traffic, racking and anything likely to strike them.
  • Drops from high level to machines in the middle of a floor are supported and protected.
  • Floor-level cables are avoided unless they are in purpose-made ducts.

Where the layout of a workshop changes often, a row of interlocked sockets or an overhead busbar system gives flexibility without rewiring for every move.

Capacity at the distribution board

Before a machine is ordered, it is worth checking that the distribution board has a spare way of the right type and that the supply to the unit can carry the additional load. A board that is full or obsolete may need replacing first; see three-phase and distribution boards.

Duties on the business

The Electricity at Work Regulations 1989 require electrical systems to be safe and properly maintained. The Provision and Use of Work Equipment Regulations 1998 require work equipment, including its means of isolation, to be suitable and maintained. The new circuit is tested and certified to BS 7671, and the certificate is kept with the site's records. Our warehouse and industrial page describes the work we do in units.

Want a fixed written quote? Call 01235 430442 or send us the details.

Frequently asked questions

It is the common name for an industrial plug and socket. They are colour-coded by voltage and made in different current ratings that are not interchangeable.

Blue connectors are for single-phase supplies at normal mains voltage. Red connectors are for three-phase supplies.

Every machine needs a means of isolating it from the supply for maintenance, which can be secured off. For plug-connected equipment the plug may serve; fixed equipment has a local isolator.

Not directly. Options include a supply upgrade or, for some machines, a suitable converter or drive. The manufacturer's advice should be followed.

No. Part P covers dwellings. Industrial premises come under the Electricity at Work Regulations 1989, with work designed and tested to BS 7671.