Skip to content
Adtec Electrical Services

Planning electrical work for a kitchen renovation

A kitchen electrical plan needs to follow the final appliance schedule and cabinet layout before walls, floors and worktops are closed up.

Short answer

Agree the appliance models, socket positions, lighting groups and isolation arrangements before first fix. An electrician must check existing circuits, demand, protective devices and cable routes rather than assuming the old kitchen supply will suit the new one. Typical UK guide costs vary widely with access and scope; Adtec gives a fixed written quote after seeing the job.

Lock down the appliance schedule first

Write down every appliance, including the hob, ovens, dishwasher, fridge freezer, washing machine, extractor and any boiling-water tap. Include model numbers and manufacturer electrical requirements where available. Similar-looking appliances can need different supplies, and a kitchen designer's drawing may not show the information needed to design the circuits safely.

Do not assume the existing cooker connection can serve every combination of new oven and induction hob. The electrician needs to assess demand, cable size, installation method and protection, alongside the manufacturer's instructions. A plug supplied with one appliance does not establish what another appliance needs, even if they occupy the same cabinet opening.

Agree who is supplying and connecting each item. The kitchen installer, appliance delivery team and electrician may have different responsibilities, and gaps between those roles can delay completion. Our cooker and hob installation service can be considered alongside the broader kitchen electrical work so connections are planned rather than left for installation day.

Check the existing installation before finalising the design

The existing socket circuit may be suitable for some additions, but that requires inspection and testing. More outlets do not increase available circuit capacity. New high-load equipment may need a dedicated circuit or changes to the distribution arrangement, and the electrician must consider the overall demand as well as the individual appliance labels.

Earthing, bonding and residual-current protection also need checking for the proposed alterations. If the consumer unit cannot accommodate the necessary protection or new circuits, that can affect both scope and timing. Discuss consumer unit upgrades early rather than discovering a board issue after the new units have blocked the cable route.

Older kitchens can hide junctions, damaged accessories and alterations made over several renovations. Access may improve once cabinets are removed, so the quotation should explain how newly exposed defects will be handled. The earthing and bonding guide explains why incoming services and their protective connections matter even when the visible project is mainly new cupboards and appliances.

Plan usable sockets and accessible isolation

Worktop outlets

Place outlets around actual preparation areas and portable appliances, with suitable separation from sinks, hobs and other sources of water or heat. There is no single simple horizontal distance rule in BS 7671 that makes every kitchen position safe; equipment instructions and the practical risk assessment still matter. Keep cables away from hot surfaces and places where they will be trapped.

Integrated appliances

Discuss how appliances can be isolated and maintained without dismantling the finished kitchen. An inaccessible plug directly behind a heavy integrated appliance may be a poor arrangement. The appropriate socket, connection point or isolator position depends on the equipment and cabinet design, and should be clearly identified where its purpose is not obvious.

Islands and peninsulas

An island supply needs a suitable cable route, often before floors are finished. Account for drawers, seating overhangs, sinks and any ventilation ductwork. Pop-up or concealed accessories are not suitable in every location. The general socket planning guide helps turn a fashionable layout into an arrangement that remains practical once the kitchen is in use.

Design lighting and extraction as part of the room

Kitchen lighting usually works best when it separates general illumination, preparation lighting and any dining or decorative lighting. Check where a person standing at the worktop will cast a shadow. Under-cabinet lighting can help, but drivers and connections need suitable locations with access for maintenance rather than being buried behind permanently fixed panels.

Choose dimmers, lamps and drivers as a compatible system. Decide which switches control each group and how the room is entered from different directions. Decorative fittings above an island should be positioned against the final island dimensions, not the centre of an early drawing that may later change. Our lighting installation service can form part of the overall kitchen plan.

Confirm the extractor type, electrical connection and ventilation route with the kitchen designer and relevant installer. Recirculating and externally ducted arrangements do different jobs, and ventilation requirements need proper consideration. If ceilings or fire-resisting elements are penetrated, the installation details must maintain the necessary performance. Electrical work should be coordinated with the building design rather than treated as the last trade to fit around everything else.

Want a fixed written quote? Call 01235 430442 or send us the details.

Typical UK guide costs for kitchen electrical work

The following are broad typical UK guide figures for planning a kitchen project in the 2025-26 market. They are not a quotation, and they are not Adtec prices. Access, region, circuit condition, the number of points and the specification can move a job outside these ranges. Several items can overlap within a larger package, so do not simply add every row together.

Typical UK guide figures, labour and materials, excluding VAT unless stated. Not Adtec prices; your job is priced after we see it.
Electrical workTypical UK guide rangeScope assumptions
Additional socket point£100–£250Straightforward accessible addition; circuit suitable
New appliance circuit£300–£900Typical domestic route; no major board work
Kitchen lighting alterations£400–£1,500Several standard fittings and controls
Kitchen electrical refit£1,500–£4,000Typical circuit alterations, sockets and lighting
Extensive kitchen electrical refit£3,000–£6,000+Difficult routes, more circuits or complex specification
Consumer unit replacement, if required£650–£1,400Typical domestic board; substantial defect repairs extra

A small change on accessible walls differs considerably from a full kitchen rewire involving solid floors, new circuits and a replacement consumer unit. Decorative lighting, specialist controls and premium accessories can add significant materials costs. Plastering, decorating, structural work, appliances and kitchen furniture are normally separate unless explicitly included in the written scope.

For an informed comparison, ask each contractor to price the same appliance list and drawing. Identify whether removal of old equipment, testing, certification and any notification are included. Agree how changes after first fix will be priced. Adtec gives a fixed written quote after seeing the job, based on the actual installation and agreed requirements rather than a universal price per kitchen.

Sequence first fix, installation and second fix

The electrician should see the final cabinet plan before first fix begins. Once the old kitchen is removed, confirm cable routes and any defects exposed by the strip-out. First fix generally installs the concealed wiring and boxes before plastering, cabinets, splashbacks and worktops prevent access. Agree positions from finished floor and worktop levels so measurements remain consistent between trades.

Before surfaces are closed, check the drawing against the room and photograph agreed cable routes. Changes to appliance positions at this stage need to be communicated to everyone affected. Our first and second fix service sets out the value of this coordination. Photographs support future planning but do not replace safe checks before drilling.

Second fix includes fitting the accessories and making the agreed equipment connections, followed by the necessary inspection and testing. New circuits are normally notifiable under Building Regulations in England; many other kitchen alterations are not automatically notifiable simply because they are in a kitchen. All work must still comply with applicable requirements. Ask for appropriate certificates and any notification evidence, with responsibilities agreed before work starts.

When to call an electrician

Bring an electrician into the project before ordering the kitchen if appliance supplies, island routes or the existing installation are uncertain. That gives the designer time to adjust details without expensive changes to manufactured units. A site assessment is especially useful when the new layout moves the hob, adds several ovens or introduces other significant electrical loads.

Stop using damaged or overheating kitchen accessories. Burning smells, scorching, repeated tripping and shocks from equipment need investigation, not concealment behind a new splashback. Isolate affected equipment only if safe and arrange professional advice. If there is smoke or fire, keep clear and use emergency services as appropriate rather than trying to finish the renovation task.

Contact Adtec with the latest drawings, appliance schedule and intended dates. Adtec Electrical Services Ltd works on domestic electrical projects and with builders and developers. A clear scope can identify the enabling work, installation stages and paperwork needed for your kitchen, while keeping assumptions and exclusions visible before the project moves into the disruptive strip-out stage.

Want a fixed written quote? Call 01235 430442 or send us the details.

Frequently asked questions

No, an existing suitable board may be retained if it can support the proposed work and protection requirements. Its condition and capacity need assessment before that decision is made.

The plan is a useful starting point, but appliance electrical details and final dimensions are also needed. Make sure revised drawings reach the electrician before first fix rather than assuming every trade has the latest version.

There will usually be planned interruptions and periods when the kitchen cannot be used normally. Agree any safe temporary arrangements in advance, especially for refrigeration and essential household needs.

The guide table describes electrical work and excludes those items unless specifically stated. A written quotation should identify all inclusions and exclusions so the wider renovation budget remains clear.

It may be possible, but circuit routes, connection positions and other services may need changing. Tell the electrician and kitchen designer immediately so they can assess the consequences before surfaces are completed.

Related pages

CallQuote