Moving a consumer unit or electric meter: who does what
Extensions, new kitchens and under-stairs cloakrooms regularly collide with the place where the electricity comes into the house. Moving the equipment is possible, but three different parties are responsible for different parts of it, and the order in which they are involved matters.
Last updated
Short answer
The service cable and main fuse belong to the distribution network operator, the meter belongs to your electricity supplier, and everything after the meter, including the consumer unit, is yours. An electrician can move the consumer unit and the wiring on your side. Only the network operator can move the incoming cable and main fuse, and only the supplier can move the meter. Moving or replacing a consumer unit must comply with BS 7671 and is notifiable under Part P in England and Wales, so it needs a registered electrician.
Where one responsibility ends and the next begins
The electricity supply arrives through a service cable, underground or overhead, which ends at a sealed unit called the cut-out. This contains the main fuse. From there, short cables run to the meter, and from the meter a pair of cables known as meter tails run to the consumer unit, sometimes through a separate isolating switch.
The cut-out and service cable are the property of the distribution network operator for your region. The meter is provided by the supplier you pay your bill to. Seals on both show they have not been disturbed. Your installation begins on the outgoing side of the meter. An electrician working for you has no authority to break the seals, remove the main fuse or relocate the meter.
Moving only the consumer unit
If the meter can stay where it is, the job is within your electrician's control. The consumer unit is installed in the new position, the meter tails are extended or replaced to reach it, and every circuit is rerouted or extended back to the new board.
The length of the meter tails is the main constraint. Tails are protected only by the network's main fuse, so suppliers and network operators limit how far they may run, commonly to around three metres. Beyond that, the usual solution is a switch-fuse fitted near the meter with a correctly protected cable from there to the consumer unit. Tails concealed in walls need suitable mechanical or additional protection as well. To connect the new tails safely the supply must be isolated, either at an isolating switch if one is fitted or by arrangement with the supplier or network operator.
Extending the circuits
Every circuit cable that reached the old board has to reach the new one. Where the move is short, cables may have enough slack or can be rerouted. Where it is longer, they are extended using properly enclosed, maintenance-free joints in accessible or permitted locations, or replaced back to a convenient point. Each joint is a potential weak spot, so a move is often the moment to consider whether older circuits should be renewed instead.
If the existing consumer unit is dated, it makes little sense to relocate it. Fitting a new unit in the new position gives current protection and avoids paying twice. See our page on consumer unit upgrades.
Moving the meter
Suppliers will usually move a meter a short distance on the same wall or board, on request, and may charge for it. Their limits vary, so ask what they will and will not do before designing around it. If the meter needs to go further, to a different wall or an external meter box, the service cable and cut-out have to move too, and that becomes a job for the network operator.
Want a fixed written quote? Call 01235 430442 or send us the details.
Moving the incoming supply
Relocating the service position means applying to the distribution network operator for a service alteration. They survey, quote, and carry out the work on the cable and cut-out. You are typically responsible for any trenching, ducting and the meter box on your land, to their specification. The supplier then attends to fit the meter in the new position, and your electrician connects the installation.
This is the slowest route and the one most often underestimated on building projects. An extension cannot be built over a live service cable without the operator's agreement, so the application should go in as soon as plans are settled.
A sensible order of work
- Ask an electrician to look at the existing arrangement and identify what has to move.
- Contact the supplier, and the network operator if needed, and obtain dates.
- Prepare the new position: meter box, ducts, backing board, cable routes.
- Network operator and supplier complete their parts.
- The electrician installs or relocates the consumer unit, reconnects circuits, tests and certifies.
On an extension or refurbishment the builder often coordinates this, but confirm who is making the applications. The electrical side of building projects is covered in our guide to extension electrics.
Earthing and bonding
A move is also the time to check the main earthing conductor and the bonding to gas and water pipework. These conductors run from the service position, and if that position changes they must be re-established at the correct sizes. Older houses frequently have undersized or missing bonding, which is corrected as part of the work.
Regulations and certification
Relocating a consumer unit is treated as a replacement for Building Regulations purposes: it is notifiable under Part P, must comply with BS 7671, and results in an Electrical Installation Certificate and a compliance certificate from the electrician's registration body or Building Control. None of this is DIY work. The equipment at the service position carries the full supply with only the main fuse to protect it.