First fix and second fix electrics: what happens at each stage
On a building project the electrician arrives, disappears for weeks and comes back again. Those visits are first fix and second fix, and the decisions a client has to make fall almost entirely before the first of them.
Last updated
Short answer
First fix is the stage when cables, back boxes, containment and any equipment hidden in the structure are installed, before plastering or boarding closes up the walls and ceilings. Second fix is the return visit after decoration is largely complete, when sockets, switches, light fittings and the consumer unit are connected. Testing and certification to BS 7671 follow. In a dwelling the work is notifiable under Part P, so it should be designed, installed and certified by a registered electrician from the outset, not signed off by someone else afterwards.
What happens at first fix
The electrician marks out the position of every socket, switch, light, appliance outlet and data point, then fixes back boxes and runs cable to each one from the consumer unit position. In timber floors and stud walls, cables pass through holes drilled within the limits that protect the strength of joists and studs. In masonry, walls are chased so that cables sit below the plaster line in the permitted zones, running vertically or horizontally from the accessory.
Cables for extractor fans, heating controls, smoke alarms, outside lights, door entry and data go in at the same stage. So do any ducts for the incoming supply and supplies to outbuildings. Earthing and bonding conductors are run while routes are open. At the end of first fix the building is full of labelled cable ends and empty boxes, and nothing is live.
Decisions needed before first fix
- Final kitchen and bathroom layouts, including appliance positions and their power requirements.
- Furniture layouts for main rooms, so sockets and switches end up where they are useful.
- The lighting scheme: pendants, downlights, wall lights, under-cabinet and outdoor lighting, and how each is switched.
- Wall and floor finishes that affect box depths, such as tiling, panelling or thick insulation.
- Data points, television positions and any wired heating or security controls.
- Provision for the future: an electric vehicle charger, a garden building, solar equipment by others.
A walk-round with the electrician before first fix starts, marking positions on the walls, prevents most later regrets. Our guide to planning sockets and switches is a useful checklist for that meeting.
Between first and second fix
Once first fix is complete, other trades take over: insulation, plasterboard, plastering, screeding, then decoration, kitchen fitting and tiling. The electrician will usually ask to inspect before walls are closed, and may carry out initial tests on the cables so that any damage is found while it is still easy to put right.
Damage in this period is the commonest cause of second fix problems. Screws and nails through cables, boxes filled with plaster, cable ends cut short or painted over, and back boxes buried behind boards all cost time. Clear communication between the builder and the electrician about what is where matters more than anything else.
What happens at second fix
With surfaces finished, the electrician fits and connects sockets, switches, light fittings, fans, appliance outlets and alarms, installs or completes the consumer unit and connects the circuits to it. Appliances such as ovens, hobs and showers are connected, and outdoor fittings are installed and sealed.
Second fix goes fastest when the rooms are finished and clear, the client's chosen light fittings are on site with their instructions, and the kitchen is complete. Fittings that arrive late, or that turn out to need a different fixing or driver from the one planned at first fix, are a regular source of return visits.
Want a fixed written quote? Call 01235 430442 or send us the details.
Testing, commissioning and handover
When everything is connected, the installation is inspected and tested circuit by circuit before being put into service. The results are recorded on an Electrical Installation Certificate with its schedules. For a dwelling, the electrician also notifies the work through their registration body, and a Building Regulations compliance certificate is issued. The client should receive both, together with a circuit chart at the consumer unit and any manufacturers' instructions.
Building Control will expect to see the electrical certification before completing a new build, extension or conversion. The different certificates are explained in our guide to EIC and minor works certificates.
Why the electrician should be involved from the start
The person who certifies an installation is confirming that the design, the installation and the testing all comply with BS 7671. Much of what they are confirming, cable routes, sizes, protection against damage, is hidden after first fix. A registered electrician cannot properly certify concealed work installed by someone else, and registration scheme rules generally do not allow it. Bringing in an electrician at the end to sign off wiring installed by another trade leads to delay, opening-up or a refusal.
For builders and developers, that is a programme risk as much as a compliance one. Our first and second fix page describes how we work with site teams on extensions, conversions and new units.
Commercial projects
The same two-stage pattern applies to shops, offices and industrial units, with differences in method. Cables are more often carried on tray, in trunking or conduit than buried in plaster, and first fix may include containment for data and other services. Part P does not apply to commercial premises, but BS 7671 does, and the completed installation is certified in the same way.