Self-build electrics: planning the installation for a new home
Building a house from scratch is the one chance to put every cable where it should be. It is also the point at which decisions made in a hurry are sealed behind plaster for decades. A clear electrical brief, agreed early, costs little and saves a great deal.
Last updated
Short answer
A self-build needs a new electricity connection from the distribution network operator, usually a temporary supply for the build, and a complete installation designed, installed, tested and certified to BS 7671. The electrical work is notifiable under Part P of the Building Regulations, so the simplest route is to appoint a registered electrician who can self-certify, and to involve them while drawings can still change. The main decisions are the size of supply, the position of the meter and consumer unit, the circuits and controls in each room, and provision for equipment you may add later.
The new connection
A plot without a supply needs a connection from the distribution network operator. They quote on the basis of the load you declare and the distance from their network, and they specify the meter position and the duct you need to lay on your land. Once the connection is made, an electricity supplier fits the meter.
The load declaration deserves care. A house with a heat pump, electric cooking, electric showers and one or two vehicle chargers may justify a three-phase supply, which is much easier to obtain at the outset than to add later. Our guide to three-phase supply explains what it offers and when it is worth requesting.
Power during the build
Trades need power long before the house has a consumer unit. The usual arrangement is a temporary building supply: the permanent service is installed to a weatherproof enclosure at the plot boundary or the future meter position, with a small distribution unit and protected sockets for site use. It must be installed and tested by an electrician, with RCD protection and equipment suitable for outdoor site conditions. When the house is ready, the supply is transferred to the permanent installation.
Meter and consumer unit positions
The meter position is governed by the network operator and supplier, who want external access where possible. The consumer unit should be close to it, to keep the cables between them short, and somewhere accessible: a utility room or plant cupboard, not a kitchen wall unit or a bedroom wardrobe. Allow more space than the board itself; controls for heating, solar equipment installed by others, and data equipment tend to gather in the same place.
Larger houses and those with outbuildings may use a main board with sub-distribution boards for an annexe, garage or plant room. Deciding that at design stage determines cable routes and duct runs under the slab and across the site.
Planning circuits and positions
The electrician designs the circuits: how sockets are grouped, how many lighting circuits there are, and dedicated circuits for cooking, showers, water heating, heat pump, vehicle charging and any outbuildings. Dividing the installation sensibly, with individual RCBO protection, means a fault affects one circuit instead of half the house.
Your part is the room-by-room brief. Mark furniture, appliances, desks and televisions on a plan, then position sockets, switches and lights to suit. Our guides to planning sockets and switches and kitchen renovation electrics work through the questions for each room.
Want a fixed written quote? Call 01235 430442 or send us the details.
Items that are easy to forget
- Mains-powered interlinked smoke and heat alarms, required for new homes.
- Extract ventilation or a whole-house ventilation system, and its controls.
- External lighting, outdoor sockets and a supply for gates or a garden building.
- Wired data points to televisions, offices and wireless access point positions.
- Heating controls, underfloor heating wiring centres and thermostat positions, as specified by the heating designer.
- Loft lighting and a socket, and power for aerial or broadband equipment.
Future-proofing
Cable is inexpensive when walls are open and disruptive to add when they are not. Sensible provision includes a duct or cable route to the parking area for a vehicle charger, where one is not being fitted at the start; a duct from the house to any likely garden building; spare ways in the consumer unit; a route from the roof to the plant area for solar equipment by a specialist installer; and deep back boxes where smart controls may be wanted. Building Regulations in England also set requirements for electric vehicle charging provision at new homes with associated parking, which your designer and Building Control will confirm for your plot.
Sequence on site
The electrical work follows the pattern set out in our guide to first fix and second fix: ducts and earthing during groundworks, first fix once the building is weathertight, second fix after decoration, then testing and commissioning. Agree with your builder or project manager when each stage falls, and who is responsible for protecting the cables in between.
Part P and certification
All the electrical work in a new dwelling is notifiable under Part P. A registered electrician self-certifies it: you receive an Electrical Installation Certificate with test results, and a Building Regulations compliance certificate is issued for Building Control, who will want it before signing off the house. If someone who is not registered carries out the work, Building Control must be told beforehand and will arrange inspection at additional cost; they do not certify work after it has been concealed. Appointing a registered electrician from the start avoids that. Our builders and developers page explains how we work on new-build projects.