Three-phase supply: what it is and when you need it
Most people only meet the phrase when an installer says a piece of equipment needs three-phase, or that their supply is too small. This guide explains the difference and how to work out whether it matters for your home or premises.
Last updated
Short answer
A single-phase supply delivers electricity on one live conductor at about 230 volts and is what most UK homes and small shops have. A three-phase supply delivers it on three live conductors, giving about 400 volts between them and considerably more capacity. You need three-phase when equipment is built for it, such as larger motors, commercial catering equipment or faster EV chargers, or when the total demand of a property is more than a single-phase supply can provide. An upgrade is arranged with the electricity network operator, and the installation work inside the building must be carried out by a qualified electrician to BS 7671.
The difference in plain terms
Electricity is distributed around the country on three phases. A cable in the street carries all three, and each house is normally connected to just one of them plus a neutral. That is a single-phase supply. Neighbouring houses are connected to different phases in turn so the load on the network stays even.
A three-phase supply brings all three phases into the building. Between any one phase and neutral the voltage is still about 230 volts, so ordinary sockets and lights work exactly as before. Between two phases it is about 400 volts. Equipment designed for three-phase uses all three together, which lets motors run more smoothly and lets a large amount of power be delivered through smaller conductors than a single phase would need.
How to tell which supply you have
Look at the incoming equipment near the meter without touching or opening anything. A single-phase supply has one main fuse carrier, usually a sealed black or grey block, with one live and one neutral tail leading to the meter. A three-phase supply has three fuse carriers side by side, or one wide unit holding three fuses, and a larger meter with more cables entering it.
The meter itself is often labelled single-phase or three-phase, or carries wording such as 3 x 230/400 V. The main switch can be a clue too: a three-phase board has a wide main switch with three or four poles operated by one handle, and its breakers are arranged in rows marked L1, L2 and L3.
If the equipment is in a locked cupboard, shared with other units or unclear, your electricity supplier or the network operator can confirm from their records. An electrician can also tell you during any visit.
When a home might need three-phase
The great majority of houses never do. A single-phase supply comfortably runs cooking, showers, heating controls and a standard home EV charger. The question arises when several large electrical loads arrive together.
- A heat pump combined with one or more EV chargers and electric cooking.
- Substantial electric heating, a swimming pool, sauna or large hot tub.
- A home workshop with machines that have three-phase motors.
- A faster EV charger than a single-phase supply can support.
- A large property, or one being divided into several dwellings.
Even then it is not automatic. An electrician calculates the realistic maximum demand, allowing for the fact that not everything runs at once. Load management on EV chargers, sensible scheduling of heating and hot water, or an increase in the main fuse by the network operator can sometimes keep a property on single-phase. Three-phase becomes the sensible answer when those options are exhausted or when a specific appliance requires it.
Want a fixed written quote? Call 01235 430442 or send us the details.
When a business needs it
For commercial premises the trigger is more often the equipment itself. Larger motors, compressors, extraction systems, lifts, bigger air-conditioning plant, commercial ovens and dishwashers, welding equipment and many machine tools are made for three-phase. The rating plate on the equipment, or the supplier's data sheet, states what supply it needs.
It also comes up when premises change use. A unit that was adequate as storage or a small office may be short of capacity as a bakery, gym or workshop. Checking the supply before signing a lease or ordering equipment avoids discovering the problem after the fit-out has started. For industrial units in particular, our guide to three-phase electrics for warehouses goes into distribution boards, sub-mains and load balancing.
How a three-phase supply is arranged
The cable into the building, the main fuses and everything up to the meter belong to the distribution network operator for your area. Only they can provide a new three-phase service or convert a single-phase one. You, or your electrician or project manager on your behalf, apply to the operator with the address, the load required and the equipment planned. They survey their network and issue a quotation.
What the upgrade involves varies widely from one address to the next. The main factors are:
- Whether three phases are already present in the street or nearby cable.
- The distance from that cable to the building and what the route crosses.
- How much excavation and reinstatement is needed, and on whose land.
- Whether the local network or substation needs reinforcing for the load.
- Whether the meter position has to move.
Once the service is in, your electricity supplier fits a three-phase meter. These steps involve different organisations and can take some time, so start the application early in any project that depends on it.
The work inside the building
After the meter, the installation is your responsibility. Moving to three-phase normally means a three-phase distribution board, new meter tails and main switchgear, checking and upgrading earthing and bonding, and deciding which circuits go on which phase. Single-phase circuits are shared out across the three phases so that no one phase carries far more than the others.
Existing single-phase equipment does not need replacing; it is simply connected to one phase and neutral. New three-phase equipment gets its own correctly protected circuit and a means of isolation. All of this is designed, installed, inspected and tested to BS 7671, and you should receive an Electrical Installation Certificate with test results.
In a dwelling, replacing the consumer unit and adding circuits are notifiable under Part P of the Building Regulations in England and Wales, so use a registered electrician who can certify the work. Three-phase equipment presents a higher voltage between conductors than a domestic supply. Never remove covers from boards or isolators, and never attempt to alter the incoming supply equipment, which is sealed for good reason.