Workplace EV charging: planning chargers for business premises

Installing one charger at a workplace is a modest job. Installing several, for staff, fleet vehicles or visitors, is a question of supply capacity and planning before it is a question of hardware.

Last updated

Short answer

A workplace charging installation starts with an assessment of the site's electrical supply and how much spare capacity it has at the times vehicles will charge. From that follow the number and rating of chargepoints, whether load management is needed to share the available power, the cable routes to the parking bays and the earthing arrangement. The distribution network operator must be involved, workplace chargepoints must meet the smart charging regulations, and the installation is designed and tested to the section of BS 7671 covering vehicle charging. Part P does not apply to commercial premises, but the work needs a qualified electrician.

Who is charging, and for how long

Staff cars parked for a working day do not need rapid charging; a moderate rate over several hours replaces a typical commute. Fleet vans that return in the evening and leave in the morning are similar. Visitor bays and vehicles that turn round quickly are a different case and may justify a higher-powered unit.

The pattern of use decides the number of chargepoints, their rating and how they are managed. It is worth writing down before any equipment is chosen: how many vehicles now, how many expected in a few years, when they arrive and leave, and whether drivers are to be charged for the electricity.

Supply capacity

The limiting factor on most sites is the incoming supply. The electrician establishes its rating and the building's existing maximum demand, ideally from logged data or the half-hourly records held by the energy supplier, not from an estimate. The difference is the headroom available for charging, and it varies through the day: a warehouse with electric heating has little to spare on a winter morning and plenty overnight.

Where headroom is short, the choices are load management, a supply upgrade from the distribution network operator, or fewer or lower-rated chargers. An upgrade can involve significant cost and lead time, so it is assessed early. Most commercial units have a three-phase supply, which allows either higher-rated three-phase chargers or single-phase units spread evenly across the phases. See three-phase and distribution boards.

Load management

Load management lets several chargers share a limited amount of power. In its static form, the group is given a fixed maximum that it divides between the vehicles plugged in. In its dynamic form, the system measures what the building is drawing and gives the chargers whatever is left, moment by moment, turning them down when the building is busy and up when it is quiet.

With dynamic control, more chargepoints can be installed on an existing supply than simple addition would allow, at the price of slower charging at peak times. It needs chargers that support it and current-measuring equipment at the incoming supply.

Distribution and cable routes

Chargepoints are normally fed from a dedicated distribution board, positioned to keep cable runs to the bays reasonable. Each chargepoint has its own circuit with the RCD protection BS 7671 requires for vehicle charging. Cables to bays away from the building run underground in ducts or as armoured cable; the groundworks are often the largest single part of the job.

If more bays are likely to be equipped later, lay ducts and draw pits to them now and size the distribution board with spare ways. The additional cost during the first installation is small compared with excavating a finished car park a second time.

Want a fixed written quote? Call 01235 430442 or send us the details.

Earthing

Vehicle charging outdoors raises a specific earthing question. On the most common type of supply, a break in the network's combined neutral and earth conductor could make the bodywork of a connected vehicle live. BS 7671 therefore requires protective measures for chargepoints on such supplies: equipment that detects the fault and disconnects, or a separate earthing arrangement for the chargers. On a site with several chargers, steel-framed buildings and buried services nearby, this is a design decision that needs proper assessment.

Chargers, mounting and protection

  • Wall-mounted units where bays are against the building; pedestals where they are not.
  • Tethered cables for convenience, or socketed units for flexibility and tidiness.
  • Bollards or wheel stops to protect pedestals from vehicle impact.
  • Bay markings, signage and lighting so the bays are usable after dark.
  • Access control and billing, by card, app or back-office system, if use is to be restricted or paid for.
  • A reliable data connection at the chargers for smart functions.

Network operator and smart charging rules

The distribution network operator must be notified of chargepoint installations, and must be asked in advance where the added load exceeds set thresholds or the adequacy of the supply is in doubt. Your installer handles the application. The Electric Vehicles (Smart Charge Points) Regulations 2021 apply to workplace as well as domestic chargepoints sold in Great Britain, so units must have smart functionality.

Grant funding for workplace chargepoints has been available through government schemes whose terms change; our guide to EV charger grants points to the official sources. Check eligibility and installer requirements before committing to equipment.

Certification and maintenance

The installation is inspected, tested and recorded on an Electrical Installation Certificate. Under the Electricity at Work Regulations 1989 the business must keep it safe, so chargers should be added to the site's periodic inspection and maintenance arrangements, and damaged cables or connectors taken out of use promptly. Our EV charger installation page covers both homes and workplaces.

Want a fixed written quote? Call 01235 430442 or send us the details.

Frequently asked questions

It depends on the supply rating and the building's existing demand. With dynamic load management, more chargers can share the available capacity than the supply could run at full power together.

Not necessarily. Single-phase chargers can be used and balanced across phases, but a three-phase supply allows higher-rated units and more of them.

The network operator must be notified, and in some cases must approve the connection beforehand. Your installer deals with this.

Yes. They apply to chargepoints sold for domestic and workplace use in Great Britain.

No. Part P covers dwellings. Workplace installations are designed and tested to BS 7671 and fall under the Electricity at Work Regulations 1989.