Installing an electric car charger at home: what happens, step by step

Having a charger fitted at home is one of the simpler electrical projects from the owner's side, but there is more going on behind the scenes than a box being screwed to a wall. Knowing the stages makes it easier to compare quotes, prepare the house and understand what you should be handed at the end.

Last updated

Short answer

A home EV charger installation runs in five stages: a survey of the property and electrical supply, any notification or application to the network operator, the installation itself on a new dedicated circuit, testing and commissioning, and handover with certification. Fitting day is usually a matter of hours for a straightforward house. The work is notifiable under Part P and must be carried out and certified by a qualified electrician.

Stage 1: the survey

Every installation starts with questions about the property. Where is the electricity meter? Where do you park? What is the route between the two? An installer may ask for photographs first and then confirm the details in person, or go straight to a site visit for anything that is not a simple run along one wall.

The survey looks at four things. First, the incoming supply: the size of the main fuse and whether the house has a single-phase or three-phase connection. Second, the earthing arrangement, because that decides what protective measures the charger needs. Third, the consumer unit: whether there is space and suitable protection for a new circuit, or whether a small separate unit at the meter is the better answer. Fourth, the cable route, including any walls to drill, floors to lift or ground to cross.

Our guide to EV charger installation requirements goes through each of those checks in more depth.

Stage 2: checking the demand on the supply

A typical home charger draws a large current for hours at a time, which is unlike almost anything else in the house. The electrician therefore adds up the existing demand, such as electric showers, cookers and heating, and compares it with what the supply can deliver.

Where the numbers are tight, there are two usual answers. One is load management: a sensor on the incoming supply tells the charger to slow down when the house is busy, so the main fuse is never overloaded. The other is asking the network operator to assess the supply for an upgrade, which we cover in our main fuse upgrade guide.

The network operator has to be informed about every charger. For many homes the installer notifies them after the work is finished. Where the property's total demand is higher, or there are known issues with the supply, an application is made beforehand and the installation waits for the reply.

Stage 3: installation day

On the day, the power is switched off for part of the visit while the new circuit is connected. The electrician fits a protective device for the charger circuit, runs the cable along the agreed route, mounts the charger at a sensible height for the parking position and makes the final connections.

  • Cable is clipped neatly to walls, run in conduit or trunking, or routed through the building where that gives a tidier result.
  • A data connection is set up, usually over home Wi-Fi, because modern chargers have smart functions that depend on it.
  • Where load management is used, a small current sensor is fitted at the meter position and linked to the charger.
  • If the earthing arrangement requires it, the charger will include protection against a fault on the supply neutral, or an earth electrode is installed.

Longer routes, charging points on detached garages and runs across driveways take more time and are quoted accordingly. The factors are set out in our guide to EV charger installation cost.

Want a fixed written quote? Call 01235 430442 or send us the details.

Stage 4: testing and commissioning

Before the charger is handed over, the new circuit is tested in line with BS 7671. That covers the continuity of the conductors, insulation resistance, polarity, the earth fault loop impedance and the operation of the residual current protection. The results are recorded on the certificate.

Commissioning is the charger's own setup. The installer sets the maximum current to suit the circuit, configures load management if fitted, connects the unit to its app and checks that a vehicle, or a test device that imitates one, starts and stops charging correctly. Chargers sold for home use in Great Britain have to offer smart functions such as scheduled charging, and they are supplied with off-peak charging hours set as the default, which you can change.

Stage 5: handover and paperwork

At handover you should be shown how to start a charge, how the app works and how to isolate the charger in an emergency. You should also receive an Electrical Installation Certificate for the new circuit. Because a new circuit is notifiable under Part P of the Building Regulations, a Building Regulations compliance certificate should follow, either through the installer's registration with a competent person scheme or through building control.

Keep these documents. They will be asked for if you sell the house, and they help any electrician who works on the installation in future. If a grant applies to your situation, the installer handling the claim must be authorised for that scheme; see our guide to EV charger grants and check current eligibility before you book.

How to prepare, and what not to attempt

The most helpful preparation is practical: clear access to the meter and consumer unit, decide where the car will normally park, and check that your Wi-Fi reaches that spot. Tell the installer about any future plans, such as a second electric car or a heat pump, because they affect the supply calculation.

A charger is not a DIY job. It involves a new high-current circuit, specific earthing and fault protection, and notification to both the network operator and building control. All of that has to be designed, installed, tested and certified by a qualified electrician. Our EV charger installation page explains how we approach the work.

Want a fixed written quote? Call 01235 430442 or send us the details.

Frequently asked questions

A straightforward installation, with the charger close to the meter and a simple cable route, is normally completed in a few hours. Long cable runs, groundworks or a consumer unit that needs attention first will add time, and the installer should tell you this at the survey stage.

For part of the visit, yes. The supply to the house has to be isolated while the new circuit is connected. It is usually a short interruption rather than the whole visit, and the electrician will tell you before switching off.

The operator must always be informed. For many homes this is a notification made by the installer after the work. If the total demand of the property is high, the installer applies first and waits for approval or for any supply upgrade.

It needs to be reachable by a safe cable route from the supply, within reach of the parking space and positioned where the cable will not be a trip hazard. Detached garages and distant parking spaces are possible but involve more work.

An Electrical Installation Certificate with the test results for the new circuit, a Building Regulations compliance certificate, and the manufacturer's instructions and warranty details for the charger itself.